One refrigeration system, carried from heat load to issued reports.

The heat load sets the cycle’s duty, the cycle’s flows size the pipes, the pipes fill in the charge — each station of Kelvin’s calculation chain starts from the one before it. Below, one example system is worked through Kelvin’s own calculation code.

Try the demo

A sample practice’s six jobs, open in the real app. No account; nothing you change is kept.

Example system
Chiller (MT) room8 × 6 × 3.5 m at 2.0 °C · single stage
Refrigerant
R-134a
Load
10.16kW
SST
−4.0°C
SCT
45.0°C
COP
3.10

Example system. Every figure on this page is Kelvin’s calculation code run on the inputs each station lists; R-134a properties are the Refrigerant Library’s migrated record. Metric units.

The calculation chain, worked on the example system

Heat Load

Transmission, infiltration, product
Takes
Heat Load’s defaults for a Chiller (MT) room: 8 × 6 × 3.5 m at 2.0 °C and 85% RH, 35.0 °C outside, 100 mm PIR panel, one 1.8 × 2.4 m sliding door with a strip curtain; the example’s product is 5,000 kg of milk (whole) pulled down from 15.0 °C over 24 h.
Heat Load readings for the example system
ReadingValue
TransmissionU × A × ΔT for each wall, the ceiling and the floor1.52kW
InfiltrationDoorway method, strip curtain0.90kW
ProductPull-down over 24 h3.05kW
InternalLighting, occupancy, material handling equipment0.68kW
Governing casePull-down; holding is 3.10 kW6.16kW
Design load(6.16 kW + 10% safety) × 24 h ÷ 16 h run time10.16kW
Defends
The duty the rest of the chain is sized to. Every component is its own line, and the holding and pull-down cases are both solved, so the plant is sized to whichever governs.

Cycle

Single stage · R-134a
Takes
10.16 kW and −4.0 °C SST handed over from Heat Load (the 2.0 °C room less the preset’s 6.0 K TD), 45.0 °C SCT at 35.0 °C design ambient, 5.0 K superheat, 5.0 K subcooling and isentropic η 0.70.
Model
Vapour-compression model on saturation properties interpolated from NIST Chemistry WebBook tables for the refrigerant (NIST Standard Reference Database 69; IIR reference state, h = 200 kJ/kg for saturated liquid at 0 °C), compression on the same table's saturated vapour carried into superheat along each isobar (Peng & Robinson 1976 residual properties, scaled to the table's own vapour heat capacity), the discharge temperature read at the discharge pressure and enthalpy; compression at the entered isentropic efficiency, not a compressor's published performance — design sizing, to be verified against the selected equipment.
Cycle readings for the example system
ReadingValue
COPCarnot 5.49 · 56.3% of Carnot3.10
Compressor powerSpecific work 46.61 kJ/kg3.28kW
Mass flowRefrigeration effect 144.24 kJ/kg0.0704kg/s
Condenser heatHeat rejection at the condenser13.44kW
Discharge tempThe temperature the discharge enthalpy sits at, h₂ = h₁ + (h(P₂, s₁) − h₁) ÷ ηs, on real vapour properties (no heat loss)67.5°C
Compression ratioPevap 252.7 · Pcond 1159.9 kPa4.59
Defends
The flows every later station reads: mass flow sizes the pipes, suction density and volumetric efficiency rate the compressor, and condenser heat is the heat-rejection duty.

Pipe Layout

Sized on velocity
Takes
The cycle’s mass flow and conditions, one evaporator on a 20 m drawn run (equivalent-length factor 1.4 suction, 1.3 liquid), and the system’s 8 m discharge and 3 m condenser-to-receiver lines.
Pipe sizes, velocities and statuses for the example system
LineVelocityStatus
Suction1 3/8″ · 20 mΔTsat 0.44 K7.20m/sPressure not judged
Liquid1/2″ · 20 mΔTsat 0.42 K0.66m/sPressure not judged
Discharge5/8″ · 8 mΔTsat 0.93 K9.39m/sVelocity low
Condenser to receiver5/8″ · 3 mΔTsat 0.02 K0.41m/sPressure not judged
Flagged
Discharge line, velocity low. Velocity 9.39 m/s against the discharge band 10.0–18.0 m/s. ΔTsat 0.93 K; compressor impact is high above 1.0 K and moderate above 0.5 K (sizing code thresholds, no cited source)
Defends
Each line's velocity against its band, its pressure and temperature against the tube maker's rating, the liquid line's subcooling margin before the TXV, and the saturation-temperature penalty on suction and discharge. A line outside a rule is flagged, with the rule it failed.

Equipment

Margin = capacity ÷ duty − 1
Takes
The cycle’s duties — what each pick’s rated capacity is judged against. This example picks no models.
Equipment readings for the example system
ReadingValue
Evaporator dutyCoolroom load per evaporator · Under 0.9× load per unit undersized; over 1.5× oversized10.16kW
Compressor dutyAt −4.0 °C SST, needing 24.60 m³/h swept · Under 0% spare undersized; over 50% spare oversized10.16kW
Heat rejectionCompressor power + cooling load · Under 1.0× heat rejection undersized; over 1.5× oversized13.44kW
Defends
Every pick against the duty it has to meet, written as spare or short, with the rule it was judged by: evaporators, compressors, condensers, valves, oil separators and receivers alike.

Refrigerant Charge

R-134a
Takes
The sized pipe run. This example picks no equipment, so no equipment charge is counted.
Refrigerant Charge readings for the example system
ReadingValue
Pipe chargeInternal volume × density at each line's conditions2.92kg
Liquid lines2.67kg
Suction lines0.20kg
Discharge line0.06kg
Total refrigerantPipe charge; no equipment or receiver in this example2.92kg
Total oil2% circulating; no compressor sump counted, as no compressor is picked0.06kg
Defends
The charge the system is filled to, and the liquid line’s flash margin: 4.6 K of subcooling left after the line’s pressure drop, so no flash gas reaches the TXV.

Operation

A seeded day · design ambient
Takes
A day seeded from the records: 240 door passages at the Heat Load’s traffic, 4 off-cycle defrosts of 20 min, the lighting, people and forklift shifts from 06:00, and the heat load’s batch arriving at 00:00, at the 35.0 °C design ambient all day. The room’s air carries its own heat capacity, 217 kJ/K.
Model
Stand-ins, not picks: a coil rated at the design duty, 10.16 kW at the preset’s 6.0 K TD and linear with TD, and 2 compressors of 12.3 m³/h each, half the swept volume the Cycle station calls for, staged on a 2.0 K suction deadband. No condenser is entered, so the condensing holds the design TD above the air and the fans aren’t judged. The batch is 400 × 300 × 300 mm crates in air at h = 15 W/(m²·K), the example’s assumption.
Operation readings for the example system
ReadingValue
Peak room airAt 06:15, with the coil off for defrost; set point 2.0 °C6.4°C
Air over set pointBy more than 0.5 K, in the door passages and defrosts; 11.7 h over it at all7.4h
Batch at midnight5,000 kg of milk (whole) from 15.0 °C, by Pham (Ch. 20); the heat load allows 24 h; stock at 2.3 °C3.5°C
Suction142 to 259 kPa g; set point −4.0 °C, 2.0 K deadband−5.0 to 5.9°C
Both compressors runningRun hours 19.4 and 7.2; 115 starts — the lead unit short-cycles through the quiet hours on the deadband's 180 s minimum run3.2h
Compressor energyFor the day, delivering 132 kWh of cooling; peak 3.34 kW40.7kWh
Defends
What the design does through a day rather than at its design point: whether the room holds its set point through the door traffic and defrosts, how the batch comes down, how the compressors stage and cycle, and where the suction sits. Every figure is the engine's, read at the cursor, and every stand-in and assumption is on the page.

Energy

Brisbane · 16 h a day
Takes
The design re-solved each month at Brisbane’s design ambient for that month (condensing = ambient + 10.0 K, not below 20.0 °C), motor efficiency 0.90, and the heat load’s 16 h a day.
Energy readings for the example system
ReadingValue
Annual energyCompressor 15,890 kWh; fans not counted15,890kWh
Average COPMean of the monthly COPs; every month solved4.23
Peak monthJan1,594kWh
Lowest monthJun1,068kWh
Not counted
No evaporator or condenser is picked in this example, so fan energy is not counted.
Defends
The running energy the running cost is built on, with each month solved at its own ambient.

BOM & Running Cost

Quantities, not prices
Takes
The charge’s pipe breakdown.
Pipe bill of materials for the example system
PipeLengthPieces
1 3/8″ suctionArmaflex AF-34.93-2520.0m4× 6 m
1/2″ liquidNot insulated by default20.0m4× 6 m
5/8″ dischargeNot insulated by default8.0m2× 6 m
5/8″ liquidNot insulated by default3.0m1× 6 m
Then
Equipment lines come from the picks and pipework from this bill — quantities only. The only money is the running cost: the energy cost and the refrigerant leak cost over the project's years.
Defends
The bill of materials, counted in whole pipe lengths, straight from the design.

Reports

PDF
Takes
The saved record from each station.
Reports Kelvin issues
ReportFrom
Heat Load reportHeat Load
Cycle reportCycle
Engineering report, technician guide and tech schedulePipe Layout
Equipment reportEquipment
Charge reportRefrigerant Charge
Operation reportOperation
Energy reportEnergy
BOM & running cost reportBOM & Running Cost
Project bundleOne PDF, each record's report starting on its own page
Defends
The document the client sees, built from the saved records as PDFs with selectable text. The Reports page names any record in the bundle that has gone stale.

Whole jobs, carried through the same chain

The example above is one room. Each worked example is a whole job: an illustrative brief with its plans, P–h diagram and schematic, and every figure Kelvin’s engine run on the brief.

All worked examples

Transcritical CO₂ supermarket pack, cycle to issued report

An illustrative transcritical CO₂ booster pack for a Brisbane supermarket — 117 kW medium temperature at −8 °C and 31 kW low temperature at −30 °C — carried through Kelvin from heat load to issued report.

Refrigerant
R-744
Gas cooler
86.3bar
COP
1.76
Charge
175kg

Restaurant coolroom and freezer room, each on its own condensing unit

An illustrative walk-in coolroom (1.73 kW at 2 °C) and freezer room (1.36 kW at −18 °C) behind a Melbourne restaurant, each on its own R-454C air-cooled condensing unit — carried through Kelvin from heat load to issued report.

Refrigerant
R-454C
Coolroom
1.73kW
Freezer room
1.36kW
Design ambient
34.8°C

Engineering requests from Deployr

Where requests come from

Requests inbox

Engineering requests raised in Deployr — from a quote, job, asset, site or project — arrive in Kelvin’s Requests inbox, grouped by the client that sent them, once your workspace is paired with Deployr. Deployr is Sentoro’s trade operations platform, a separate product.

Lifecycle

  1. Received
  2. In progress
  3. Awaiting information
  4. Review required
  5. Approved
  6. Report issued
  7. Complete

Steps

  1. ReviewDone once the status has moved on from Received
  2. ContextDone once Deployr's context is on the request
  3. Link designDone once a system design is linked
  4. Selection & pushDone once a push has been sent to Deployr
  5. IssueDone once reports have been emailed to the client

No account needed: refrigerant pressure–temperature tables and P–h diagrams for 28 refrigerants, with each one’s GWP, ODP and safety class; a superheat and subcooling calculator and printable P–T charts; and the worked examples.

Put your own system through the chain

Create an account with your email address and confirm it with the code Kelvin sends you. Already have one? Sign in.

Note

Verify before implementation

Kelvin’s calculations are design aids based on published industry methods and standard thermodynamic and hydraulic models. They do not constitute automatic compliance with AS/NZS, EN or other codes — every result, including the example on this page, must be verified by a qualified refrigeration engineer before implementation.